The Port of Savannah handled 565,366 TEU in October, up 25% on a year ago. It was the second-busiest month in the Georgia Ports Authority's history.

The Port of Savannah handled 565,366 twenty-foot equivalent container units (TEU) in October. That is up 25% on October 2025. A TEU is one 20-foot shipping container, the industry’s standard measure.

It was the second-highest monthly total in the Georgia Ports Authority’s history. The authority reported the figures Tuesday in a news release on October volumes.

Overview

  • October 2026: 565,366 TEU through Savannah, up 25% from October 2025
  • Ships: 160 vessels called in October, up 5% from a year earlier
  • Fiscal year to date: volumes up 7.8%, or 152,991 TEU
  • September 2026: 504,015 TEU, a record for that month, up 3.7%

Why the authority says volumes rose

CEO Griff Lynch put the jump down to consumer demand and the length of this year’s shipping peak.

“Our container volumes are driven by strong consumer spending, an extended peak shipping season and our port and inland infrastructure ease of use,” Lynch said in the release.

Authority President Kevin Price pointed to ocean carriers going back to routes through the Suez Canal. He said that cuts 10 to 12 days off transit times to Savannah during the holiday shopping season.

The release also noted that the Panama Canal raised its daily vessel transits from 33 to 34 from Nov. 12. The canal authority also raised the maximum draft at its largest locks from 49 to 50 feet, according to the release.

October against September

October’s total was 61,351 TEU higher than September’s, which the authority reported as a record for that month. In its September release, the authority said peak volumes had been pushed later in the year by typhoon delays at Asian ports.

Bar chart of Port of Savannah container volume: 504,015 TEU in September 2026 and 565,366 TEU in October 2026. Source: Georgia Ports Authority news releases, Oct. 7 and Nov. 17, 2026.
Monthly totals as reported by the Georgia Ports Authority. Chart by Savannah News Today.
Share this chartFacebookWhatsAppX

Where the river projects stand

The release gave updates on the authority’s building work in Savannah:

  • the $1.6 billion rebuild of Ocean Terminal is more than 60% complete and will raise its capacity from 200,000 TEU to 1.75 million TEU
  • truck gate construction and support services there are 99% complete
  • the $2.3 billion Savannah Container Terminal on Hutchinson Island, permitted Oct. 14, is due to start construction in 2028
  • the authority is working with the U.S. Army Corps of Engineers on a study into deepening the shipping channel and adding passing lanes for two-way ship traffic

Once the new terminal is built, the authority expects the Port of Savannah’s total capacity to reach 12 million TEU a year.

What it means for you

The containers arrive and leave by truck and train. The authority says Savannah handles 15,000 truck gate moves a day and 42 double-stack trains a week. Its October release did not say how those figures changed last month.

The authority is donating $6 million to a workforce housing program in port communities. It said the program has helped more than 230 families repair, buy or build a home in the Savannah area since it began in September 2023.

The release did not give a job figure for October or say how long the higher volumes are expected to last. Its subheading said the authority forecasts strong demand through the end of the year.